Description

Both side headlamps (HI) are not turned ON when setting to the lighting switch HI or PASS.

Diagnosis Procedure

1.COMBINATION SWITCH INSPECTION

Check the combination switch. Refer to BCS-92, "Symptom Table".

Is the inspection result normal? YES >> GO TO 2.

NO >> Repair or replace the malfunctioning part.

2.CHECK HEADLAMP (HI) REQUEST SIGNAL INPUT

1. Select “HL HI REQ” of IPDM E/R data monitor item.CONSULT-III DATA MONITOR


1. Select “HL HI REQ” of IPDM E/R data monitor item.

2. With operating the lighting switch, check the monitor status.

Is the inspection result normal?


Is the inspection result normal? YES >> GO TO 3.

NO >> Replace BCM. Refer to BCS-93, "Removal and Installation" (with Intelligent Key), BCS-161, "Removal and Installation" (without Intelligent Key).

3.HEADLAMP (HI) CIRCUIT INSPECTION

Check the headlamp (HI) circuit. Refer to EXL-45, "Component Function Check".

Is the inspection result normal? YES >> Replace IPDM E/R.

NO >> Repair or replace the malfunctioning part.

    Exterior lighting system symptoms
    Without daytime running light system WITHOUT DAYTIME RUNNING LIGHT SYSTEM : Symptom Table CAUTION: Perform the self-diagnosis with CONSULT-III before the symptom diagnosis. Perform the trouble di ...

    Both side headlamps (LO) are not turned on
    Description Both side headlamps (LO) are not turned ON in any condition. Diagnosis Procedure 1.CHECK COMBINATION SWITCH Check the combination switch. Refer to BCS-92, "Symptom Table". ...

    Other materials:

    Air cleaner and air duct
    Exploded View 1. Hose clamp 2. PCV hose 3. Hose clamp 4. Air cleaner filter 5. Air cleaner filter case 6. Grommet 7. Inlet air duct (lower) 8. Grommet 9. Inlet air duct (upper) 10. Bracket 11. Air cleaner case 12. O-ring 13. Mass air flow sensor 14. Air duct A. To electric ...

    Auto operation does not operate but manual operate normally (driver side)
    Diagnosis Procedure 1.PERFORM INITIALIZATION PROCEDURE Initialization procedure is executed and operation is confirmed. Refer to PWC-16, "Work Procedure". Is the inspection result normal? YES >> INSPECTION END NO >> GO TO 2. 2.CHECK ENCODER CIRCUIT Check encoder c ...

    Turbocharger boost control
    Turbocharger boost control : SystemDiagram Turbocharger boost control : System Description INPUT/OUTPUT SIGNAL CHART SYSTEM DESCRIPTION Depending on driving conditions, the ECM performs ON/OFF duty control of the turbocharger boost control solenoid valve and controls the boost by adjustin ...